Celebrating Substantial Completion

After more than eight years of construction, The Nevada Department of Transportation is bridging the transportation gap in northwest Las Vegas with the substantial completion of the U.S. 95/CC 215 interchange, also known as the Centennial Bowl. This major milestone also marks the completion of the U.S. 95 Northwest Corridor Improvements Project, a major multi-phase infrastructure project to improve connectivity for the growing communities in northwest Las Vegas.

Watch the above video to see the Centennial Bowl Progress over the years.

U.S. 95 NORTHWEST CORRIDOR IMPROVEMENT PROJECT

After more than a decade of design and construction, the $579 million, 13- mile U.S. 95 Northwest Corridor Improvements Project represents a crucial development for the region by improving transportation connectivity and promoting economic growth.

TIMELINE

timeline

INTERACTIVE MAP

Click on the interactive map below to learn more about the benefits of each phase of the project.

Phase 1

COMPLETE

Phase 1 View details
  • Increased traffic capacity of the 6-mile stretch between Washington Avenue and Ann Road.
  • Enhanced HOV access.
  • Improved Safety.
  • Installed waterwise features to enhance the visual aesthetics of the area.
  • Completed in Summer 2013

Phase 2

COMPLETE

Phase 2A View details
  • Increased highway capacity for the three miles between Ann Road and Durango Drive.
  • Enhanced HOV access.
  • Installed waterwise features to enhance the visual aesthetics of the area.
  • Improved regional connectivity
    • Completed in Fall 2015

COMPLETE

Phase 2Bincludes Phase 5 View details
  • Upgraded the stretch of freeway between Ann Road and Kyle Canyon Road and built an interchange at Kyle Canyon Road
    • Completed in Summer 2019

Phase 3

COMPLETE

Phase 3A View details
  • Extensive improvements made to U.S. 95 to increase capacity and safety of U.S. 95/CC 215 interchange, also known as the Centennial Bowl, and improved flood safety of areas north of Las Vegas.
    • Completed in August 2017

COMPLETE

Phase 3C View details
  • Created a system-to-system interchange at the Centennial Bowl with new ramp connections.
    • Completed in Summer 2021

Substantially Complete

Phase 3D View details
  • Completed the Centennial Bowl interchange and implemented landscape and aesthetic features.
    • Substantially Completed in December 2023

Phase 4

COMPLETE

Phase 4 View details
  • Improved connectivity for existing and future communities in northwest Las Vegas through the construction of an interchange at Skye Canyon Park Drive, formerly known as Horse Drive.
    • Completed in Winter 2011

Phase 5

COMPLETE

Phase 5included with Phase 2B View details
  • Upgraded the stretch of freeway between Ann Road and Kyle Canyon Road and built an interchange at Kyle Canyon Road
    • Completed in Summer 2019

BENEFITS

U.S. 95 Widening

HOV Access Ramps

Improved Connectivity

Aesthetics

Stormwater System

Enhanced Technology

Improved Travel Time Reliability

Reduced Emissions

Improved Safety

PROJECT CONTACT

Fred Shakal, P.E.

Project Manager
775-888-7589
fshakal@dot.nv.gov

MEDIA CONTACT

Justin Hopkins

NDOT Public Information Officer
725-208-2771
jhopkins@dot.nv.gov